Projects

rmms hollister

 

Client: Hollister ULC Ballina Co Mayo

Mechanical Contractor: Kirby Group

Project Name: Hollister Fluid Management System

Building Type: Pharmaceutical

Start Date: January 2015

End Date: July 2015 (Phased work)

Description of Work

  • Supply, Fabrication & Installation of 2”/1 ½”/1” & ½” Stainless Steel High Purity Pipework for the Fluid Management system
  • Final Connection to Clean Room Machines
  • Supply & Installation of High Purity Valves & Instrumentation
  • Bracketry
  • NDT Testing
  • Full Documentation Package
  • Welds carried out by GTAW Orbital Welding Procedure

 

 

 

Client: Pharmaceutical Plant Westport

Mechanical Contractor: ERBA Engineering

Project Name: B/C Producion Area AHU5a Clean Steam High Purity Pipe Installation

Building Type: Pharmaceutical

Start Date: April 2016

End Date: May 2016

Description of Work

  • Supply, Fabrication & Installation of 1” Stainless Steel High Purity Clean Steam Pipework
  • Supply & Installation of High Purity Valves & Instrumentation
  • Bracketry
  • NDT Testing
  • Passivation
  • Full Documentation Package
  • Welds carried out by GTAW Orbital Welding Procedure

 

 

 

Client: Healthcare Facility Castlebar

Mechanical Contractor: Raymond Masterson Mechanical Services Ltd

Project Name: Sterilizer Water Recovery Project

Building Type: Pharmaceutical

Start Date: January 2016

End Date: June 2016

Description of Work

  • Supply, Fabrication & Installation of 8” Stainless Steel 316L Sch 10 Pipework & Fittings for Flow & Return Header.
  • Supply, Fabrication & Installation of 6” Stainless Steel 316L Sch 10 Pipework & Fittings to Recovery Tank & Hot Storage Tank
  • Supply, Fabrication & Installation of 4” Stainless Steel 316L Sch 10 Pipework & Fittings for Flow & Return to 13 no Sterilizers
  • Supply & Installation of Valves & Instrumentation
  • Cladding & Insulation
  • Bracketry
  • Welds carried out by TIG Welding Procedure

 

 

 

Client: Healthcare Facility Castlebar, Co Mayo

Mechanical Contractor: Raymond Masterson Mechanical Services Ltd

Project Name: Fluid System Tank Complex Upgrade

Building Type: Pharmaceutical

Start Date: January 2012

End Date: July 2014 (Phased work)

Description of Work

  • Supply, Fabrication & Installation of 6”/4”/3”/2 ½”/2”/1 ½”/1”/ ¾” & ½” Stainless Steel High Purity Pipework for DI Water & Solution Lines in the upgrade of the Fluid System Tank Complex
  • Supply Fabrication & Installation of Fluid Transfer Panels
  • Final Connection to Tanks/Pumps
  • Supply & Installation of High Purity Valves & Instrumentation
  • Bracketry
  • NDT Testing
  • Full Documentation Package
  • Welds carried out by GTAW Orbital Welding Procedure